In exclusive statements to “Sharjah 24”, Al Marzouqi confirmed that the project includes the construction of 29,000 meters of main sewer lines and 15,000 meters of branch lines, in addition to the construction of two pumping stations. This will increase the network's efficiency and serve the targeted areas.
35% of the project has been completed and expected to be done by early 2027. The project will serve residential units, commercial centers, schools, and other facilities in Al Muwafjah and Al Yash, boosting infrastructure and meeting community needs.