Engineer Nasser bin Shabib, Deputy Director of the Energy Transmission Department at SEWA, explained that converting cables was carried out according to the best specifications, quickly and with high efficiency. He added that the work teams succeeded in implementing the project by adjusting the operation of the electrical network in the region, without affecting the population, and continuity of services.
Engineer Nasser bin Shabib pointed out that the 132 kV cable lines tracks, which were diverted, exceeded 2500 metres.