Engineer Ahmed Al Bass, Deputy Director of the Electricity Distribution Department, confirmed that SEWA has made significant strides in strengthening the energy infrastructure and improving the performance of the electrical grid. As part of the project, six substations have been installed and connected, along with 14 electricity distribution panels, ensuring a stable and efficient power supply.
Additionally, more than 29 kilometres of electrical cables have been laid. This includes 22.17 kilometres of medium-voltage cables linking the substations and 7.6 kilometres of low-voltage cables to provide power to residential buildings.